400901
Jan 15, 2009 - Mar 13, 2009
$750,000
DEEWR - 414 LaTrobe St Melbourne
Department of Education, Employment and Workplace Relations (DEEWR)

Architect: Interiors Australia

Project Description:
Fast tracked staged fitout of three occupied floors in the old Customs House (414 LaTrobe St.). The ten week program involved demolition of offices followed by construction of new offices, meeting rooms, breakout areas, supply and installation of detailed joinery, and procurement of loose furniture and workstations, new carpet, paint, and blinds throughout.. Services additions included new lighting, communications cabling, supplementary air conditioning systems and alterations to existing power, fire and security systems.

Form of Contract Used:  Deed of Standing Offer

Total Project Cost
Original Contract Sum: $ 640,500
Final Contract Sum: $750,000

Project Duration
Original Contract Completion Date: 14 March 2009
Final Completion Date: 14 March 2009

Reasons for any Delays:
No delays to project Details of any contract disputes No contractual disputes to report. Additional information SMI delivered this project in 10 weeks, including procurement of loose furniture and workstations.

 
<< Back
Home  |  About us  |  Leadership  |  Careers  |  Contact us
SMI Project Services  |  SMI Building Services  |  SMI Fire Services  |  News & Events
Sitemap  |  Privacy Policy  |  Terms of use
©-2008 SMI Group Pty Limited, All rights reserved.
Website Design & Website Development by Sigma Infotech