Architect: HBO + EMTB Project Description: Fast tracked staged fitout in an occupied floor of the Australian Passport Office at Casselden Place. Approx. 1600 sqm over 8 weeks, the project involved the construction of new offices, meeting rooms, breakout area, supply and installation of detailed joinery, and procurement of loose furniture and workstations. Services additions included new lighting, communications cabling, supplementary air conditioning systems and alterations to existing power, fire and security systems. Form of Contract Used: MBA BC3 Lump Sum Contract Total Project Cost Original Contract Sum: $ 540,500 Final Contract Sum: $678,000
Project Duration Original Contract Completion Date: 21 November 2008 Final Completion Date: 21 November 2008 Reasons for any Delays: No delays to project
Details of any Contract Disputes: No contractual disputes to report. Additional information SMI delivered this project in 9 weeks, including procurement of loose furniture and workstations. |